Pre-design tool for water transfer networks.

This tool supports preliminary design of water transfer lines from source to destination. Results do not replace engineering calculation with actual elevation profile and pump curves.

What the inputs mean

  • Flow rate — the volume to be moved per unit time
  • Route length — the real pipe length, not the straight-line distance on a map
  • Elevation difference — the lift the pump has to overcome
  • SDR and PN — the pipe class, which sets wall thickness and therefore the bore

What the calculation rests on

Friction head loss uses Hazen-Williams with a roughness coefficient C of 145 for polyethylene — the smooth bore of PE is what justifies a value that high. Total head is the elevation difference plus friction loss, and motor power follows from total head and flow rate with a reserve percentage applied.

Why velocity is the constraint

The tool computes velocity for each candidate diameter and flags anything outside roughly 0.5 to 2.5 m/s. Below 0.5 there is a risk of suspended solids settling out. Above 2.5, head loss climbs quickly, pumping energy gets expensive and surge on rapid valve closure becomes a more serious concern. The recommended diameter is the smallest one that keeps velocity inside that band.

What it does not calculate

  • The real elevation profile and any high points along the route
  • The pump curve and its actual duty point
  • Surge and transient pressure
  • Local losses at fittings, valves and bends
  • Temperature derating above the 20 °C reference

From result to order

The output is an effective internal diameter and a pipe class. To enquire, take the outer diameter and SDR from the catalogue dimensions chart and quote those. If the operating temperature is above 20 °C, apply the derating factor before fixing the SDR.

FAQ

Which formula is used for HDPE pipe head loss?
Hazen-Williams with a roughness coefficient C of 145 for polyethylene. For tighter work, or for fluids other than water, Darcy-Weisbach with a computed friction factor is the better basis.
Why are several diameters offered for one flow rate?
Because diameter selection is a trade. A larger bore cuts head loss and pumping energy but costs more in pipe. The tool shows every option with its velocity and loss so the trade is visible.
Is the calculated pump power the motor I should buy?
No. It is an estimate from total head and flow with a reserve applied. Final motor selection has to come from the pump curve, the real efficiency at the duty point and the starting conditions.
Does it check for surge?
No. Surge needs a separate calculation and depends on valve closure speed, line length and flow velocity. On long lines or at higher velocities, check it separately.

Preliminary water transfer line estimate — well depth (20 m) is excluded from total head. Total head equals vertical lift (150 m) plus line friction loss.

  • Hazen-Williams C = 145 for PE pipe
  • Pump efficiency = 0.75
  • Well depth excluded from total head
Preliminary recommendation: External diameter 90 mm — velocity 0.65 m/s — total head 464090.1 m — power 19391.23 kW

Results

OD mmSDRPNe mmID mmv m/shf mH mkWStatus
3211161.4526.185.1671448251.4971448401.492985352.38High velocity
4011161.8232.733.3024095887.7724096037.771006812.78High velocity
5011162.2740.912.118126326.338126476.33339551.27OK
6311162.8651.551.332636266.632636416.63110158.28OK
7511163.4161.360.941127596.541127746.5447121.01OK
9011164.0973.640.65463940.07464090.0719391.23OK
11011165.0090.000.44174563.48174713.487300.11Low velocity
12511165.68102.270.3493654.4693804.463919.46Low velocity
14011166.36114.550.2753924.6754074.672259.42Low velocity
16011167.27130.910.2128139.0028289.001182.01Low velocity
18011168.18147.270.1615854.2216004.22668.71Low velocity
20011169.09163.640.139489.879639.87402.79Low velocity
225111610.23184.090.105346.835496.83229.68Low velocity
250111611.36204.550.083200.453350.45139.99Low velocity
280111612.73229.090.071842.771992.7783.26Low velocity
315111614.32257.730.051038.261188.2649.65Low velocity
355111616.14290.450.04579.98729.9830.50Low velocity
400111618.18327.270.03324.30474.3019.82Low velocity
450111620.45368.180.03182.72332.7213.90Low velocity
500111622.73409.090.02109.37259.3710.84Low velocity
560111625.45458.180.0262.97212.978.90Low velocity
630111628.64515.450.0135.48185.487.75Low velocity

Results are for preliminary design only and do not replace verified engineering calculations. Final pump and pipe selection must consider pump curves, operating pressure and the actual elevation profile.